12 Dec 2001, 18:48 UTC
FW: Bushton Processing Shut Down Plan - Receipt Point C6+ Listing
- From
- Lynn Blair lynn.blair@enron.com
- To
- John Sturn
- Date
- Wed, 12 Dec 2001 10:48:52 -0800 (PST)
John, I am not as smart as you are. I did not know the Hexanes are C6+. Thanks for the education. Lynn
Quoted or forwarded from earlier messages
-----Original Message----- From: January, Steve Sent: Wednesday, December 12, 2001 12:13 PM To: Blair, Lynn Subject: FW: Bushton Processing Shut Down Plan - Receipt Point C6+ Listing -----Original Message----- From: Sturn, John Sent: Wednesday, December 05, 2001 1:10 PM To: Ashland, Team; Beatrice-M&O, Team; Team Beatrice-Purple; Beaver-Plant, Team; Pool, Eddie; Burdett, Team; Bushton-Maintenance, Team; Bushton-Operations, Team; Clifton, Team; Ellis2, Team; Cunningham, Team; Holcomb-Fld-Comp, Team; Holcomb-Maint, Team; Holcomb-Oper, Team; Hugoton-Field, Team; Hugoton-Plant, Team; Hugoton-SE, Team; Hugoton-SW-MTCO, Team; Hugoton-SW-TXCO, Team; Lyons, Team; Macksville, Team; Mullinville-Maintenance, Team; Mullinville-Operations, Team; Mullinville Pipeline Team; Oakland, Team; Palmyra-1, Team; Palmyra-Plant, Team; Perryton, Team; South-Omaha, Team; Spearman, Team; Sublette, Team; Sunray-Compressor, Team; Sunray-Field, Team; Tate, Team; Tescott, Team; Alvarado, Jesse; Armitage, Roy; Barnes, Rodney; Barry, Richard; Braswell, Keith; Calhoun, Rory; Coash, Steve; Cochran, Jeffrey; Cummings, Helen; Ellington, Michael; Hall, Margaret; Hardy, Crandal; Henley, Gaynel; Monden, Bart; Moore, Jeff; Munson, Robert; Spain, Ron; Welsh, Edward; January, Steve; Ratliff, Dale; Schoolcraft, Darrell; Spraggins, Gary Cc: Gilbert, Tom; Poock, Brian; Tippin, Wally; LeBeau, Randy; Jordan, Fred; Lowe, Mickey; Williams, Walt; Gaines, David; Mall, Greg; Hallowell, Dean; Peschka, Mike; Odneal, Dave; Nelson, John; Rice, Tom; Wood, Byron; Stephens, LD; Howard, Randy; Dietz, Laverne; Miller, Dave W; Noyes, David; Graham, Charlie; Kile, Rick; Aschwege, Doug; Faucheaux, Eric Subject: Bushton Processing Shut Down Plan - Receipt Point C6+ Listing Attached is the latest listing of Bushton Universe receipt points with their corresponding C6+ compositions. As you recall this list is to be used with the Bushton Procesing shut down plan to determine what receipts may have to be curtailed in the event of a shut down of the Bushton processing plant. Eric Faucheaux is working with ETS Measurement Technology to set up a process to regularly update this list. In the future these updates will not be emailed, but will be available on Optimization website, under Operating Guidelines. The Optimization team website is at: http://www.ets.enron.com/optimization/ A corp id and login are required to access the site.