Links Meeting Summary & Lean Gas Conf. Call

From
Jerry Graves jerry.graves@enron.com
To
Randy Rice, team.ashland@enron.com, team.beaver-mach-shop@enron.com, team.beaver-plant@enron.com, bob.besecker@enron.com, david.boothe@enron.com, team.burdett@enron.com, Team Bushton-Maintenance, team.bushton-operations@enron.com, team.bushton-safety@enron.com, Team Cunningham, team.cunningham-safety@enron.com
and 72 more bill.dyer@enron.com, team.ellis2@enron.com, John Ford, bill.foresman@enron.com, dean.hallowell@enron.com, team.holcomb-fld-comp@enron.com, team.holcomb-maint@enron.com, team.holcomb-oper@enron.com, randy.howard@enron.com, team.hugoton-field@enron.com, Team Hugoton-Plant, team.hugoton-se@enron.com, team.hugoton-sw-mtco@enron.com, team.hugoton-sw-txco@enron.com, fred.jordan@enron.com, joy.lewis@enron.com, kelly.lewis@enron.com, Mickey Lowe, team.lyons@enron.com, team.lyons-safety@enron.com, team.macksville@enron.com, greg.mall@enron.com, dave.miller@enron.com, team.mullinville@enron.com, team.mullinville-maintenance@enron.com, team.mullinville-operations@enron.com, team.mullinville-safety@enron.com, john.noland@enron.com, david.noyes@enron.com, team.pampa@enron.com, team.pampa-overhaul@enron.com, team.perryton@enron.com, eddie.pool@enron.com, tom.poston@enron.com, Dan Pribble, ray.reed@enron.com, jimmie.smith@enron.com, team.spearman@enron.com, LD Stephens, team.sublette@enron.com, team.sunray-compressor@enron.com, team.sunray-field@enron.com, team.tate@enron.com, will.trujillo@enron.com, Walt Williams, bob.alabbasi@enron.com, ccrawford@enron.com, crobertson@enron.com, david@enron.com, dkurth@enron.com, hickey.don@enron.com, muse.jay@enron.com, jknight@enron.com, jrburdge@enron.com, jschulz@enron.com, willts.kevin@enron.com, hoggatt.ray@enron.com, jones.roger@enron.com, rvargo@enron.com, Gary E. Anderson, ken.anderson@enron.com, judy.beck@enron.com, controllers.dl-ets@enron.com, chuck.good@enron.com, Jerry Graves, david.kolarik@enron.com, sigrid.macpherson@enron.com, Gary Maestas, jim.mcclain@enron.com, carol.sommer@enron.com, John Sturn, roger.westfall@enron.com
Cc
Jo.Williams@dynegy.com, morgan.gottsponer@dynegy.com, Dave.Neubauer@dynegy.com, vernon.mercaldo@dynegy.com, penny.mccarran@dynegy.com, steven.d.thomas@dynegy.com
Bcc
Jo.Williams@dynegy.com, morgan.gottsponer@dynegy.com, Dave.Neubauer@dynegy.com, vernon.mercaldo@dynegy.com, penny.mccarran@dynegy.com, steven.d.thomas@dynegy.com
Date
Wed, 27 Feb 2002 13:02:31 -0800 (PST)
FYI,
Here is a summary of the Links meeting and the Lean Gas Conference call. The meeting and conf. call went very well. I want thank everyone for their participation. Please use the notes below, and the attached outage report (at the bottom) to follow the plans for April / May outages. The report is sorted by start date. This is the schedule, and I will true up the estimated flow affects with Ken Anderson in the next week, or so. Please give me a call if you have any questions.

Mullinville South Lean Side ESD's 04/30/02
Spearman A Line leak repair will start on 4/28, and the station ESD will be 4/30. They should be back up with 25 mmcf in 4 hours.
Mullinville plant will be down 4/30 for 12 hours. Beaver 1 & 2, and the Clark 1 & 2 will be down until Mullinville comes back up. 
Beaver plant will go down 4/30, but will come back up in 4 hours.
Northrup & Perryton Barlow will go down on 4/30 for 8 hours.
Beaver Southeast and gathering station ESD's will be staggered through the end of May and into June and July to reduce flow impact.  

Holcomb & Field ESD's 05/02/02
Holcomb will be down 2 to 4 hours. 
Tate, Burdett, and the Finney stations will go down the same time frame.

Hugoton & Field ESD's 05/07/02 to 05/09/02
Hugoton will be down until the evening of the 9th.(2 ? days)
Sublette will go down 05/07 and come back on as soon as they have gas to pump. (Estimating around noon).
Stevens 4 & 6 will be down completely through the Hugoton outage. (2 ? days)
Stevens 1,2,3,and 7 will come back on about 10:30am 05/07 to by-pass through Hugoton.
Morton 1& 6 will come back on about 2:00pm 05/07.
Texas 1 & 2 will be down until 05/08. When the Oxy wells come back on.
Dave Gilmore, (EOG) has been notified of our May outage schedule. 

Bushton ESD 05/07/02
The Bushton ESD will be 05/07 along with Hugoton. They will be down for 12 hours.

Jerry Graves
713-345-8923