TW Bullets Week of March 11
- From
- Darrell Schoolcraft darrell.schoolcraft@enron.com
- To
- Donna Scott
- Date
- Fri, 15 Mar 2002 07:56:37 -0800 (PST)
* TW March 2002 Average Daily Receipt 1,854
TW March 2002 Average Daily Delivery 1,802
* During the week of March 11 a total of 291,474 mmbtu was made available for marketing's
intra-month operational sales by managing line pack and coordinating OBA imbalances.
* During the week of March 11 a total of 46,986 mmbtu was accommodated for Rides
* During the week of March 11 a total of 40,000 mmbtu was accommodated for Parks.
* March 15, A Force Majeure was posted until further notice at the Bisti Compressor Station
located on the San Juan Lateral.
The problem appears to be electrical. Personnel are on site evaluating the situation.
Volume affected will be approximately 80,000 mmbtu/d.
* Work was completed on time at Station 4 and Station 1.