25 May 2001, 22:02 UTC
(no subject)
- From
- Michael Frazier michael.frazier@enron.com
- Date
- Fri, 25 May 2001 15:02:28 -0700 (PDT)
Please note that the IBM load (approximately 40 MW per hour) in the PGE3 demand zone that was expected to be returned to PG&E bundled service on June 1 is now expected to remain a scheduling and supply obligation for EES. A complete hourly schedule for June 1, including IBM and incorporating all known changes confirmed by that time, will be sent on Tuesday May 29. In addition, a sample "flash report" based on weather-corrected load projections and the explanation of available forecast detail will be sent on Tuesday. Please call me at 713-345-3200 or Michael Spruiell at 713-345-8644 for questions. Thanks Michael