Thanks for the updates.
If you have any more customer calls please send them to me if you need to.

Thanks DS
Quoted or forwarded from earlier messages
-----Original Message-----
From: 	Carr, James  
Sent:	Monday, October 29, 2001 6:54 AM
To:	Carr, James; Blair, Jean; Bryan, Randy; Walden, Shirley; Callans, Nancy; Perry, Renee; Porter, Diana; Wilkens, Jerry; Clapper, Karen; Barry, Patrick; Washington, Kathy; Schoolcraft, Darrell
Cc:	Spraggins, Gary
Subject:	RE: TRAILBLAZER OUTAGE 

Darrel attached is an e-mail sent out to the North Team approved by Gary concerning the Trailblazer outage.  Gary did not plan on posting the rescheduled Trailblazer outage for Nov. 8, since it will not affect throughput.

James

 -----Original Message-----
From: 	Carr, James  
Sent:	Friday, October 26, 2001 2:50 PM
To:	Carr, James; Blair, Jean; Bryan, Randy; Walden, Shirley; Callans, Nancy; Perry, Renee; Porter, Diana; Wilkens, Jerry; Clapper, Karen; Barry, Patrick; Washington, Kathy
Cc:	Spraggins, Gary
Subject:	RE: TRAILBLAZER OUTAGE REVISION

This is a correction to the Trailblazer outage, the outage has been rescheduled for Nov. 8 and is an outage on NNG side of the pipe.
Per Gary this outage has been worked out between both Trailblazer and our Gas Controls to not affect throughput.

James

 -----Original Message-----
From: 	Carr, James  
Sent:	Thursday, October 25, 2001 3:38 PM
To:	Carr, James; Blair, Jean; Bryan, Randy; Walden, Shirley; Callans, Nancy; Perry, Renee; Porter, Diana; Wilkens, Jerry; Clapper, Karen; Barry, Patrick; Washington, Kathy
Subject:	RE: TRAILBLAZER OUTAGE

This information is for internal use only, Gary Spraggins is not going to post this outage on our Web. Site.

James

 -----Original Message-----
From: 	Carr, James  
Sent:	Thursday, October 25, 2001 2:42 PM
To:	Blair, Jean; Bryan, Randy; Walden, Shirley; Callans, Nancy; Perry, Renee; Porter, Diana; Wilkens, Jerry; Clapper, Karen; Barry, Patrick; Washington, Kathy
Subject:	TRAILBLAZER OUTAGE

The outage planned at Trailblazer Beatrice Point 1318 for Oct. 30 has been rescheduled for Nov. 6 by NGPL.  This is a 16 hours outage on NGPL side of the pipe and is not a NNG outage. This information was supplied by Gerry Graves of System Planning.

James