Enron email

Algorithmic Indexing

8 Feb 2000, 18:22 UTC

Re: Request for 7FA estimate

From
Bruce Golden bruce.golden@enron.com
To
Tracee Bersani
Date
Tue, 8 Feb 2000 10:22:00 -0800 (PST)
Tracee

Best data we have for a 7FA simple cycle is the East Coast Power Linden #7 
that NEPCO did.

EPC cost for single unit was $63,000,000 based on a $34,000,000 7FA cost. 
Scope was for 7FA with CO catalyst and stack, generator breaker, main power 
transformer, 4160 V switchgear, 480 switchgear, small control room, light oil 
tank and pumps for backup fuel, natural gas heater.

Best data we have for 7FA combined cycle is Pittsburg.

Simple cycle matrix

unit config net capacity long term net heat rate long term estimated total 
project EPC cost
  kW   Btu/kWhr HHV  $total (not including IDC, escalation, Owners costs, 
development costs)
dry operation
1 GE 7FA 146118   11238   $65,750,000  $450/kWnet
2 GE 7FA 292235   11238   $123,075,000  $421/kWnet
3 GE 7FA 438353   11238   $177,250,000  $404/kWnet

water injection for summer power
1 GE 7FA 163792   11250   $68,750,000  $420/kWnet
2 GE 7FA 327585   11250   $128,775,000  $393/kWnet
3 GE 7FA 491377   11250   $185,500,000  $378/kWnet

Combined cycle matrix

dry operation
1 X 1 CCGT 221255   7417   $140,280,000  $634/kWnet
2 X 1 CCGT 448295   7321   $255,220,000  $569/kWnet
3 X 1 CCGT 676780   7274   $369,040,000  $545/kWnet

water injection for summer power
1 X 1 CCGT 244777   7523   $143,640,000  $587/kWnet
2 X 1 CCGT 496037   7424   $258,580,000  $521/kWnet
3 X 1 CCGT 748919   7376   $372,400,000  $497/kWnet

This is better data than what Ben Rogers got on Paducah. I was able to get a 
better CCTG model run so performance is better than my wild guess Monday. EPC 
cost is roughly same basis, did do some adds and subtracts based on your 
memo. May not have captured everything but should be in the ball park. 
Numbers should be useful for conceptual screening proformas to see if we are 
in ballpark, we should do a tasking letter and a complete conceptual 
scope/performance/estimate if you need any numbers that we might base 
something we put on an offer table. Obviously not reviewed or approved by 
anybody.

Ben

I will rerun your data in same form for Paducah - should look better

Thanx Bruce
Quoted or forwarded from earlier messages
Tracee Bersani@ECT
02/08/2000 02:13 PM
To: Bruce Golden/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT
cc: Greg Blair/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Mike 
Coleman/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT 

Subject: Request for 7FA estimate

Bruce,

Per my voicemail, I am requesting an estimate for 7FA capital costs and heat 
rate for a proposed expansion of an IPP acquisition. We will be putting 
together a model to come up with an all-in capital cost ($/kw) for a single 
cycle, and possibly combined cycle facility with 1-3 7FAs and 0-1 steam 
turbines.  The maximum MW of the site would be approximately 500 MW, so we 
would like to consider the following configurations: 

1, 2, or 3 gas turbines single cycle, for a total of 170, 340, or 510 MW.
2 gas turbines plus one steam turbine in combined cycle, for a total of 510 
MW. 

Here are some specifics about the facility:
located in Lakewood NJ (east PJM)
primary fuel is natural gas, with a back up fuel of heavy fuel oil
expansion on site of current 238 MW combined cylce facility (2 ABB GT 11N1, 
w/ ABB KT Steam turbine )
for option 1: peaking facility, 25% dispatch
for option 2: baseload facility, 90% dispatch
total capacity of pipe is 150 MMcf, and current project uses only 30 MMcf 
(e.g. sufficient gas pipeline)

From my discussions with Ben Rogers, I understand that the numbers were 
approximately $34-36 MM/turbine and installed capital cost was $571/kwh for 
27FAs in combined cycle, at a heat rate of 7300.

Please let me know if this information is enough to get an estimate of the 
turbine costs, heat rate, VO&M, start-up costs, and fuel requirements.  
Please give me a call when you get this so we can pick a time to discuss the 
project further. 

Regards,
Tracee