Rob 

Can you make sure that the Toronto Office is not blowing their minds on 
costs.
Quoted or forwarded from earlier messages
---------------------- Forwarded by John J Lavorato/Corp/Enron on 09/20/2000 
07:37 AM ---------------------------
   
	
	
	From:  Kevin M Presto @ ECT                           09/18/2000 05:29 PM
	

To: John J Lavorato/Corp/Enron@Enron, Mark Dana Davis/HOU/ECT@ECT
cc: Lloyd Will/HOU/ECT@ECT, Mitch Robinson/Corp/Enron@Enron 

Subject: PI Installation Report


I totally support having a separate marketing and trading team in Ontario to 
focus on the opening of that market.  However, with respect to creating a 
redundant physical system operation/real-time unit monitoring/dispatch 
function in Ontario, it simply does not make economic or logistical sense.  
With the integration of the  6 peaker plants into our operation and the 
associated IT support, control area operations, plant operations, hourly 
trading, and real-time monitoring system here in Houston, we could provide 
all the necessary tools and support personnel necessary to perform this 
function from Houston.   All the critical trading information would obviously 
be available to the Ontario office, yet they would not have to be burdened by 
the additional overhead to build a stand alone physical operation.

From my standpoint, it just doesn't make sense to re-create the physical 
capabilities the Houston office has developed over the past two years.  The 
Ontario guys are doing a great job and I like their aggressive attitude, 
however, rationale business decisions should still prevail.

Your thoughts?
---------------------- Forwarded by Kevin M Presto/HOU/ECT on 09/18/2000 
05:01 PM ---------------------------


Lloyd Will
09/18/2000 03:41 PM
To: Garrett Tripp/TOR/ECT@ECT, Paul Devries/TOR/ECT@ECT, Jan 
Wilson/TOR/ECT@ECT, Jeff Borg/TOR/ECT@ECT
cc: Mitch Robinson/Corp/Enron@Enron, Kevin M Presto/HOU/ECT@ECT, Dana 
Davis/HOU/ECT@ECT, Edward D Baughman/HOU/ECT@ECT 
Subject: PI Installation Report


Attached is the data you requested today.   The schematic detail requested 
can be found in the email attachment at the bottom of this email.  Please 
also contact Ed Baughman on the TIE proposal for dispatching, scheduling and 
trading services that was recently done to leverage of the existing Genco 
facilities and staff.

On the dedicated ring downs all work was co-ordinated by Darren Adamik 
(713-853-4764) if you require additional details.

Generally it will take 4 staff for a 24 hour operation plus one vacation/sick 
relief.  Depending on the complexity of the operation you will have to 
determine the level of industry expertise.  A good plan would be to hire a 
senior lead utility type and then bring on junior staff.  The quality and 
quantity of staff will likely be based on the value at risk and the 
complexity of dispatching these units. 

If you consider the operation critical a diesel and UPS will be required.

Plasma displays run $10,000 to $15,000 per display plus any switching/av 
equipment.

We have a PI consultant on contract that could be available for your PI 
project - typically $ 150.00 per hour plus travel and expenses.

The above assumes that no special hardware/software is required from The IMO 
to dispatch these units.

______________________________________________________________________________
_______________
I have also attached the initial PI project spreadsheet for your review and 
the following email for our PI order.

Please issue Two Purchase Orders to:
OSI Software, Inc
Attention: Richard Crounse
Fax Number 281-920-6199

Enron Software Licensing Contact: Gene Diers, x36361
Charge to Company Number 34K (East Power Generation - GENCO), RC 2176, Work 
Order S30084

These purchase orders need to be issued by December 14.  Time is of the 
essence.  The attached quotation from OSI Software is for reference.

One purchase order should be titled:  Remote Monitoring - OSI PI Software 
System
The amount is:    $ 304,571.25

Item    Description
PI-BP    Server Base Package   $  75,000
PI-IN-STANDARD-NT  OSI Standard Interfaces   $  60,000
Custom Interfaces  Custom Interfaces   $  35,000
PI-IN-ES-HABSC  Esca HABITAT-SCADA   $    5,000
PI-Manage   Process, Datalink, ODBC, Batch  $  21,725
PI-ActiveViewer   Web Enabled View   $  15,000
PI-API    Application Programming Interface $    1,250
PI System Manuals  PI System Manuals   $    1,000
PI Client Manuals  PI Client Manuals   $    2,000
PI-ActiveViewer Manuals PI ActiveViewer Manual   $            0

PI TSA Pricing   Technical Support Annual Fee  $  88,596.25


The second purchase order should be titled: Remote Monitoring - OSI PI 
Software Services
The amount (Not to Exceed) is:  $ 157,750
This purchase order is to be a Not-To-Exceed to cover variable costs as they 
get charged for installations services, travel and living expenses, and 
training.  The final invoiced amount is likely to be different from that 
ordered.

Item    Description
On-site Custom   On-site Custom Services  $  50,000
Installation   Installation Services   $  67,500
Training   Training Services   $  35,400






---------------------- Forwarded by Lloyd Will/HOU/ECT on 09/18/2000 02:30 PM 
---------------------------


Ramesh Swaminathan@ENRON
09/18/2000 01:49 PM
To: Lloyd Will/HOU/ECT@ECT
cc:  
Subject: PI Installation Report



FYI
---------------------- Forwarded by Ramesh Swaminathan/Corp/Enron on 
09/18/2000 01:48 PM ---------------------------
   
	Enron North America Corp.
	
	From:  Richard Broussard                           08/22/2000 03:24 PM
	

To: Art Stappenbeck/ECP/Enron@Enron
cc: Bill Viola/ECP/HOU/ECT@ECT, Brian Peteler/ECP/Enron@Enron, John 
Snell/ECP/Enron@Enron, John Brady/ECP/HOU/ECT@ECT, Tom 
Milillo/ECP/HOU/ECT@ECT, Mitch Robinson/Corp/Enron@Enron, Madhup 
Kumar/Corp/Enron@ENRON, Alan Chen/Corp/Enron@Enron, Ramesh 
Swaminathan/Corp/Enron@ENRON 

Subject: PI Installation Report


Art,

Please find attached my report on the PI installation at the ECP plants.  If 
all goes as expected, we should be wrapped up by September 1.  The total cost 
to date is approximately $75K with an additional $33K expected.  Please call 
if you have any questions.

Regards,
Rick Broussard
(713) 853-5316