29 May 2001, 13:23 UTC
Re: NWPL Facility Agreement
- From
- Gerald Nemec gerald.nemec@enron.com
- To
- Ken
- Bcc
- Scott Josey, Steve Pruett
- Date
- Tue, 29 May 2001 06:23:00 -0700 (PDT)
Ken, Attached is the Northwest Pipeline FA with my comments incorporated. I have attached both a clean and a redlined version. Please note that I added a cap to the total facilities costs. This is a recommendation. To the extent we have no cap however, Crescendo is at risk for all costs they incur. Cost overruns could be significant. Please review and let me know if you have any questions.