9 Nov 2001, 20:04 UTC
RE: Genco/ROC
- From
- Tammy R. Shepperd r..shepperd@enron.com
- Date
- Fri, 9 Nov 2001 12:04:33 -0800 (PST)
Perhaps I should rephrase. Do you wish for any work to continue on the ROC at this time, or shall we put it on the back burner for a couple of weeks? If the ROC is to be operational in early 2002, any further efforts towards the project will begin to incur external costs. Lloyd and Fred are working on a management briefing for you. Tammy
Quoted or forwarded from earlier messages
-----Original Message----- From: Kitchen, Louise Sent: Thursday, November 08, 2001 5:44 PM To: Shepperd, Tammy R. Subject: RE: Genco/ROC Absolutely not. We never did this on any of the other stuff. -----Original Message----- From: Shepperd, Tammy R. Sent: Thursday, November 08, 2001 5:01 PM To: Kitchen, Louise Subject: Genco/ROC Louise, Do you want Lloyd and Fred to obtain construction drawings (CD's) so that a project estimate can be generated on the ROC? The CD's will run between $25 - 45,000. Thanks, Tammy