21 Mar 2002, 19:36 UTC

GPM Dumas

From
Gary Spraggins gary.spraggins@enron.com
To
controllers.dl-ets@enron.com
Date
Thu, 21 Mar 2002 11:36:14 -0800 (PST)
  GPM Dumas will be shutting their process plant down in the morning Friday, March 22, through Tuesday, March 26th. During this time Sunray will  switch them from the C-line to the B-line so it can be taken to the inlet of Bushton. Spearman and Sunray will be coordinating the switching of valves. Hutch 1 will have to be shut-in during this time since they were using the B-line to freeflow into the suction of Spearman. All parties have been notified.
Gary