El Paso Maintenance - Opportunity?
- From
- Lorna Brennan lorna.brennan@enron.com
- To
- Steven Harris, Jeffery Fawcett, Lorraine Lindberg, Kevin Hyatt, TK Lohman, Michelle Lokay, Lindy Donoho, Jo Williams
- Date
- Thu, 11 Jan 2001 01:39:00 -0800 (PST)
El Paso has postponed Line 1300 and Line 1301 maintenance projects on the San Juan Crossover until February. Flagstaff Station and the Navajo 2D turbine will be down Jan. 22-23, cutting North Mainline capacity by 50 MMcf/d. One Rio Vista turbine will be down Jan. 22-25, limiting capacity of the IEXCPT37 and IGCNMX37 interconnects to a total of 125 MMcf/d.