31 May 2001, 13:17 UTC
EFI/DPC FMA
- From
- Doug Leach doug.leach@enron.com
- Date
- Thu, 31 May 2001 06:17:00 -0700 (PDT)
In light of the impending arbitration proceedings between DPC and MSEB should we file a third party beneficiary claim against MSEB regarding the Fuel Management Agreement? The FMA is not part of Enron's equity in the plant, but is directly related to MSEB's performance under the PPA. EFI is due $2.5 million per year in monthly installments, fluctuating with the plant's availibility and based on DPC being paid by MSEB. Currently $13.8 million of MTM value and approximately $21 million of acurral (non PV dollars) is at risk on Enron's books. The DPC plant went commercial in May, 1998 so there are seventeen (17) years left on the FMA. What if anything should we do to protect EFI's interest?