Phase IV Worry List

From
Rockford Meyer rockford.meyer@enron.com
To
jordan.hunter@enron.com, Dan Pribble, Wiley Cauthen, david.sinclair@enron.com
Date
Fri, 14 Jan 2000 06:46:00 -0800 (PST)
This week's Worry List of items which could adversely impact commencement of 
construction include the following:

 1.  Submerged Lands Permit
 2.  DEP Permit
 3.  Babcock appeal of the DEP Permit
 4.  DCA Clearance
 5.  Turbidity Exception
 6.  Punta Gorda Approval
 7.  Corps. of Engineers
 8.  ROW Acquisition

On Monday at our conference call we will need to discuss each of these items, 
strategy for timely resolution, and the person directly responsible for 
driving the resolution of these items.

Rock