31 Aug 2001, 19:25 UTC
FW: Beaver Southeast Dehy Outage
- From
- Lynn Blair lynn.blair@enron.com
- To
- Larry Berger, Lynn Blair, Michael Bodnar, John Buchanan, Terry Kowalke, Raetta Zadow, Jean Adams, Robert Benningfield, Tangie Dykes, Sherry Forbish, Chris Greaney, Scott Hibbard
- Date
- Fri, 31 Aug 2001 12:25:33 -0700 (PDT)
FYI. Thanks. Lynn
Quoted or forwarded from earlier messages
-----Original Message----- From: Spraggins, Gary Sent: Friday, August 31, 2001 1:36 PM To: Neubauer, Dave; Williams, Jo; Miller, Kent; Neville, Sue; Mercaldo, Vernon; January, Steven; Blair, Lynn; Corman, Shelley Subject: Beaver Southeast Dehy Outage The Beaver field team and GPM ( Duke) have agreed to have the Beaver Southeast Dehy outage on Sept. 11th. They plan to have all their work completed and back in service in 24 hours. Affect flow for this outage is 160,000 mmbtu. This was posted on the bulletin board today. If you have any questions please give me a call. Gary