4 May 2001, 16:24 UTC
Austin - TD of I Hours
- From
- Eric Booth eric.booth@enron.com
- To
- Kay Mann
- Date
- Fri, 4 May 2001 09:24:00 -0700 (PDT)
Kay- Go ahead and issue the breakout contract as is for the LM6000's at Austin. I will give you some wording for a change order to increase the number of TD of I hours and days of per diem. The way the contract is written, it will save us money to issue a change order as opposed to changing the base number of hours in the contract. Sections 2.0 and 8.0 of Exhibit H-1 states that over time hours within the original 240 hour total are deduducted at time and a half. Total TD of I hours worked in excess of the 240 hour total are only marked up by 22%. (Straight time = $135/hr, overtime = $165/hr) I will give you some wording as soon as I get an estimate from the field on how many days of per diem will be used. Thanks, Eric Booth