25 May 2001, 11:57 UTC
FW: letter
- From
- Greg Krause greg.krause@enron.com
- To
- Kay Mann
- Date
- Fri, 25 May 2001 04:57:00 -0700 (PDT)
Kay, is this what you meant? Consistent with the results of the Feasibility and Facilities Studies and discussions that have been held to date between Florida Power & Light Company (&FPL8) and Midway Development Company, L.L.C (& Midway and its designees referred to as &MDC8), by this letter MDC authorizes FPL to perform the necessary studies, analysis and other activities required to develop and support a schedule the necessary for a potential power project to interconnect with FPL,s transmission grid system and receive back-feed by March 15, 2002. Does this letter get the "Oricle's" seal of approval? If Ben needs to sign this, would it be ok if he faxed it to FPL?
Quoted or forwarded from earlier messages
-----Original Message----- From: Mann, Kay Sent: Friday, May 25, 2001 9:05 AM To: Krause, Greg Subject: letter My suggestions: