28 Apr 2001, 04:36 UTC
Status of Deviation Actualizations - October Preliminaries
- From
- Caroline Emmert caroline.emmert@enron.com
- Date
- Fri, 27 Apr 2001 21:36:00 -0700 (PDT)
I have started the actualization process with 403 Load Deviation, and need to work closely with TJ on Monday to find out why the allocations don't match the variances. I have isolated one day, zone and hour and will work on that with him. We have got to get it working properly, or else there will be a lot of manual work required. 404 Export Deviation is complete for October, and the records can be set to A with the other days as normal. 405 Import Deviation needs the new calcs that will be provided by a re-run of SettleSupplemental, which I am going to kick off just before I leave. I will run that on Monday while TJ is researching the 403 errors/problems. 402 Gen Deviation will also be started on Monday. Tentative target date for completion of Prelim's is next Thursday, and Finals on Friday. See you Monday. Caroline