22 May 2001, 12:46 UTC
FW: SRP Transmission Line Losses March 2001
- From
- Tom Alonso tom.alonso@enron.com
- Date
- Tue, 22 May 2001 05:46:39 -0700 (PDT)
The sender added no text of their own; everything below is quoted or forwarded.
Quoted or forwarded from earlier messages
-----Original Message----- From: Thompson, Virginia Sent: Monday, May 21, 2001 11:13 AM To: Fischer, Mark; Alonso, Tom Subject: SRP Transmission Line Losses March 2001 Dear ST-SW, I have added deal # 615628 for 3-31-01 to account for Line Loss charges on transmission reserved by the ST-SW desk during March 2001. The calculation is as such: ($769,538.28 total) x (2.3% of total Kilowatt hours of energy provided) = $17699.38 for MWh Detail is in your box. Please contact me with any questions. Thanks, Virginia