TW/ Questar new interconnect -------Level "B" release cost estimate

From
Mansoor Abdmoulaie mansoor.abdmoulaie@enron.com
To
Earl Chanley
Cc
Kimberly Watson, Ron Matthews, Dennis Alters, Perry Frazier, Morgan Gottsponer, Darrell Schoolcraft, Rich Jolly, David Roensch, Norm Spalding
Bcc
Kimberly Watson, Ron Matthews, Dennis Alters, Perry Frazier, Morgan Gottsponer, Darrell Schoolcraft, Rich Jolly, David Roensch, Norm Spalding
Date
Thu, 10 Jan 2002 12:57:11 -0800 (PST)

Per Kim Watson request of 1-10-2002, please develop a scope and "B" release cost estimate to tie Questar - 12" line to TW-30" - Blanco Hub at suction side of the Bloomfield Compressor Station in San Juan County, New Mexico as shown in the attached station- schematic.


Volume design:		80-120 mmcf/ d
Pressure:		870-920 psig
Gas Quality:		Blanco Hub gas
Specific Gravity:		 0.60
Line segment No: 	Call you tomorrow on this.			

Facility requirements as discussed with Questar in November-2001:

Tap& Valve
Meter run 
H2o monitor
Chromatograph
Pressure/ Flow Control-valves
Positive shut-in
EFM
DAS
GFC