31 Jan 2001, 16:24 UTC
Fwd: DJ Calif Asked For Revisions To Util Audit Language -Source
- From
- Jeff Dasovich jeff.dasovich@enron.com
- To
-
Alan Comnes, angela.schwarz@enron.com, beverly.aden@enron.com, bill.votaw@enron.com, brenda.barreda@enron.com, Carol Moffett, cathy.corbin@enron.com, Chris H Foster, christina.liscano@enron.com, Christopher F Calger, craig.sutter@enron.com, Dan Leff
and 76 more
debora.whitehead@enron.com, Dennis Benevides, Don Black, Dorothy Youngblood, Douglas Huth, Edward Sacks, eric.melvin@enron.com, Erika Dupre, Evan Hughes, fran.deltoro@enron.com, Frank Vickers, gayle.muench@enron.com, Ginger Dernehl, Gordon Savage, Harold Buchanan, Harry Kingerski, Iris Waser, James D Steffes, James W Lewis, james.wright@enron.com, jeff.messina@enron.com, Jeremy Blachman, Jess Hewitt, Joe Hartsoe, Karen Denne, Kathy Bass, Kathy Dodgen, Ken Gustafson, kevin.hughes@enron.com, Leasa Lopez, Leticia Botello, Mark S Muller, marsha.suggs@enron.com, Marty Sunde, Meredith M Eggleston, Michael Etringer, Michael Mann, Michelle D Cisneros, Mike D Smith, mpalmer@enron.com, Neil Bresnan, Neil Hong, Paul Kaufman, paula.warren@enron.com, Richard L Zdunkewicz, Richard Leibert, Richard Shapiro, Rita Hennessy, Robert Badeer, Roger Yang, Rosalinda Tijerina, Sandra McCubbin, Sarah Novosel, Scott Gahn, Scott Stoness, Sharon Dick, skean@enron.com, Susan J Mara, tanya.leslie@enron.com, Tasha Lair, Ted Murphy, Terri Greenlee, Tim Belden, tony.spruiell@enron.com, Vicki Sharp, Vladimir Gorny, Wanda Curry, William S Bradford, Kathryn Corbally, Jubran Whalan, triley@enron.com, Richard B Sanders, Robert C Williams, Greg Wolfe, Dirk vanUlden, steve.walker@enron.com - Date
- Wed, 31 Jan 2001 08:24:00 -0800 (PST)
The sender added no text of their own; everything below is quoted or forwarded.
Quoted or forwarded from earlier messages
----- Forwarded by Jeff Dasovich/NA/Enron on 01/31/2001 04:24 PM -----
"Ronald Carroll" <rcarroll@bracepatt.com>
01/31/2001 02:33 PM
To: <acomnes@enron.com>, <jdasovic@enron.com>, <mary.hain@enron.com>,
<smara@enron.com>
cc:
Subject: Fwd: DJ Calif Asked For Revisions To Util Audit Language -Source
----- Message from "Tracey Bradley" <tbradley@bracepatt.com> on Wed, 31 Jan
2001 08:56:51 -0600 -----
To: "Andrea Settanni" <asettanni@bracepatt.com>, "Jeffrey Watkiss"
<dwatkiss@bracepatt.com>, "Paul Fox" <pfox@bracepatt.com>, "Ronald Carroll"
<rcarroll@bracepatt.com>
Subject: DJ Calif Asked For Revisions To Util Audit Language -Source
FYI
DJ Calif Asked For Revisions To Util Audit Language -Source
Copyright , 2001 Dow Jones & Company, Inc.
LOS ANGELES (Dow Jones)--California utility regulators sent a draft audit of
Edison International (EIX) unit Southern California Edison's financial
condition back to accounting firm KPMG LLP to have "conclusionary statements
and value judgments" removed, a person working closely with the state on the
issue said Tuesday.
"They made some value judgments, but their job was simply to provide an
audit," the person said. As a result, the California Public Utilities
Commission told the auditors "to go back and take out the value judgments and
make their findings neutral," the person said.
The final audit, released late Monday, is decidedly different from an
executive summary of a draft lawmakers held last week, according to several
Democratic lawmakers who said they had seen a copy.
For one, last week's executive summary clearly stated that the utilities
can recoup billions of dollars from consumers retroactive to August 2000, one
Democratic senator said.
KPMG and the California Public Utilities Commission declined to comment.
The Public Utilities Commission requested independent audits of Southern
California Edison and PG&E Corp. (PCG) unit Pacific Gas & Electric Co. in
late December to determine the validity of their claims that soaring
wholesale power costs would force them into bankruptcy unless their rates
were allowed to rise.
The audit of Pacific Gas & Electric, being prepared by Barrington
Wellesley Group, had yet to be released late Tuesday.
KPMG's final audit shed some light on the severity of Southern
California Edison's liquidity crisis and outlined payments the utility has
made to its parent company. But it made no recommendations on whether the
Public Utilities Commission should grant the utility's request for a rate
hike or declare at an end the rate freeze that has kept it from passing its
power costs on to customers.
The audit says Southern California Edison has paid $4.5 billion more for
electricity than it was allowed to charge consumers. It also says the utility
has paid $4.8 billion to its parent company since deregulation, with the bulk
of that sum being paid out to shareholders via dividends or share buybacks.
One adviser to a Democratic assemblyman said it was proper for the
Public Utilities Commission to send the audit back to KPMG.
"I would have done the same thing," the adviser said. "This is a very
charged issue."
-By Jason Leopold; Dow Jones Newswires; 323-658-3874;