11 Apr 2001, 12:21 UTC
ERCOT Ancillary Services Methodology
- From
- Thane Twiggs thane.twiggs@enron.com
- To
- Doug Gilbert-smith, Clint Dean, Smith L Day, Eric Saibi, Mike Curry, Martin Lin, Ron McNamara, Thane Twiggs, Jean Ryall, Michelle Parks, Christi L Nicolay
- Date
- Wed, 11 Apr 2001 05:21:00 -0700 (PDT)
There are several items worth noting regarding the ERCOT's methodology: Regulation Reserve Requirements (RGRS). ERCOT has determined that 600 MW of Reg up and down will be adequate for 95% of the hours during the year, if historic patterns hold and if balancing energy is deployed properly. During what ERCOT considers to be "high stress" periods, they will increase their normal RGRS requirement by a multiple of 2-3. The initial start-up of the single control area will be considered "high stress" and ERCOT will purchase 2-3 what is necessary to cover the inexperience of the operators. This will be the practice until ERCOT is comfortable with the single control area (or until market participants complain about the high cost of A/S). The high stress option will remain available for the first year of operations. Non-Spinning Reserve Requirements (NSRS). ERCOT proposes to a methodology of purchasing NSRS only when projected risk of insufficiency is higher than normal, or large amounts of spinning reserve are not projected to be available online based on resource plans.. This boils down to where the temperature is projected to be greater than 92 degrees, less than 32 degrees Fahrenheit or uncertain and when spinning reserves less than 4600 MW are projected. Here is the process: 1. Review the weather forecast for the next day and see if it differs significantly from the current day. 2. If the next day forecast is &similar8 to the current day forecast, and the current day forecast high temperature is <92, and the current day low temperature is greater than 32 degrees, and the current day generation plan shows >4600 MW of spinning reserve online all day long, and the current month is not April, May, or October, THEN no NSRS is considered to be required all day for the next day. 3. Else: Purchase NSRS using the following: ? If the current month is April, May or October, then purchase NSRS in amounts equal to the largest unit online for the hours projected within 80% of peak hour. ? If today,s and tomorrow,s ERCOT high temperature is projected above 92 degrees, then purchase NSRS in amounts equal to the largest unit online for the hours projected warmer than 92 degrees. ? If tomorrow,s low temperature forecast is projected below 30 degrees, then purchase NSRS in amounts equal to the largest unit online for the projected morning load pickup hours and hours projected within 80% of peak hour. Purchase amounts of NSRS equal to the largest unit online for hours in which the Day Ahead operator estimates spinning reserves online will drop lower than 4600 MW. Replacement Reserve Requirements (RPRS). The requirement will be set at the amount of RPRS required to resolve supply inadequacy, CSC, and OC (local) congestion simultaneously. There will be procurement of RPRS if the resource plans indicate capacity inadequacy based on the QSE scheduled load with the ERCOT projected load. If the ERCOT projected load is greater than the QSE scheduled load and capacity available in the resource plan does not cover the difference, then there is a capacity inadequacy problem. If the CSC flows based on the QSE schedules are greater than the limits, then the CSC problems are recorded. Then a transmission contingency analysis will be run to identify OC constraints. If the flows are greater than the limits, the OC flow values are recorded. When there are insufficient RPRS bids for ERCOT to resolve its reliability and security concerns, ERCOT may choose to request OOM capacity or to use RMR units. ERCOT will use the scheduling pricing dispatch (SPD) to determine which OOM and RMR units should be selected and when to discontinue OOM/RMR service. Balancing Energy Requirement. ERCOT's goal for balancing energy is (1) to use BES so that regulation service in either direction is not depleted, (2) to minimize net energy in regulation, and (3) to provide frequency control when frequency is high, especially during minimum load intervals. ERCOT will use a two-step approach to calculate balancing energy service needs. Step one will be to clear the balancing energy service market resolving load-generation balances and Zonal congestion (local congestion is ignored). Step two is to determine the balance energy service needs to resolve local congestion as well as generation-load balance and zonal congestion. The desired result of step two is to minimize the cost of local congestion which will be an uplift to the market. Balancing Energy Down Bid Percentage Requirement. This will be used for congestion management and frequency control (to correct for high frequency). ERCOT will evaluate the export amount of each congestion management zone and transmission transfer capability between CM Zones. If the export amount is greater than the calculated transfer capability of a CM Zone, then the difference between these two values is the potential congested MW, or the total MW of DES Down bids needed for clearing Zonal Congestion. Also sufficient down bid percentage requirement will be determined by ERCOT. Market rules dictate that by 0600 of the day ahead QSEs will be notified of this percentage requirement for BES down bids by Congestion Zone. Responsive Reserve Requirement (RRS). The RRS requirement is set at 2300 MW for all hours under normal conditions. Interruptible responsive reserve cannot exceed 25% of the QSE total requirement. For the initial start-up period of the market, ERCOT will have the tendency to over buy ancillary services while the are "adjusting" to the single control area. Thane Thomas Twiggs Enron Corp 1400 Smith Street Houston, Texas 77002 713-853-3199 Voice 713-408-4463 Mobile 713-646-8272 Fax 877-968-8967 Digital Pager or 8779688967@skytel.com
Quoted or forwarded from earlier messages
----- Forwarded by Thane Twiggs/ENRON_DEVELOPMENT on 04/10/2001 04:59 PM ----- Thane Twiggs 04/10/2001 03:42 PM To: Doug Gilbert-Smith/Corp/Enron@ENRON, Clint Dean/Corp/Enron@Enron, Smith L Day/HOU/ECT@ECT, Eric Saibi/Corp/Enron@ENRON, Mike Curry/Enron@EnronXGate, Martin Lin/Contractor/Enron Communications@Enron Communications, Ron McNamara/NA/Enron@Enron, Thane Twiggs/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Jean Ryall/NA/Enron@ENRON, Michelle Parks/Enron@EnronXGate, Christi L Nicolay/HOU/ECT@ECT cc: Subject: ERCOT Ancillary Services Methodology The attached file was large so I will provide the link to the ERCOT website. If you cannot down load and would like a hard copy, let me know. http://www.ercot.com/currents.htm -- It is under Ancillary Services Methodologies. Thane Thomas Twiggs Enron Corp 1400 Smith Street Houston, Texas 77002 713-853-3199 Voice 713-408-4463 Mobile 713-646-8272 Fax 877-968-8967 Digital Pager or 8779688967@skytel.com ----- Forwarded by Thane Twiggs/ENRON_DEVELOPMENT on 04/10/2001 03:38 PM ----- Thane Twiggs 04/10/2001 03:04 PM To: Doug Gilbert-Smith/Corp/Enron@ENRON, Clint Dean/Corp/Enron@Enron, Smith L Day/HOU/ECT@ECT, Eric Saibi/Corp/Enron@ENRON, Mike Curry/Enron@EnronXGate, Martin Lin/Contractor/Enron Communications@Enron Communications, Ron McNamara/NA/Enron@Enron, Thane Twiggs/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Jean Ryall/NA/Enron@ENRON, Michelle Parks/Enron@EnronXGate, Christi L Nicolay/HOU/ECT@ECT cc: Subject: ERCOT Ancillary Services Methodology Attached is the proposed ERCOT ISO methodology for determining A/S Purchases. The methodologies will be presented to the ERCOT Board for approval April 17, 2001. Thane Thomas Twiggs Enron Corp 1400 Smith Street Houston, Texas 77002 713-853-3199 Voice 713-408-4463 Mobile 713-646-8272 Fax 877-968-8967 Digital Pager or 8779688967@skytel.com