Response to Redrock Air Permit Delay

From
Larry Campbell larry.campbell@enron.com
To
Louis Soldano, Richard Melton
Date
Mon, 17 Sep 2001 05:33:00 -0700 (PDT)
John, I read Phil's statements concerning the Redrock air permit issue and 
would like to shed some additional light concerning the reason why  
Transwestern  did not know about the delay in the agencies issance of the air 
permits.  I had met with each agency prior to submitting each application to 
ensure that each application contained the correct and proper information 
required by the EPA and State of Arizona.  When I told them that we were 
expecting the permits by the end of September, each agency indicated that a 
September permit issuance would not be a problem, in light of the fact that 
energy issues were to be given top priority in the State of Califonia.   I 
phoned the  permit engineer assigned to each application monthly to be kept 
aware of possible conflicts and resolve any concerns.  In all monthly calls, 
both agencies assured me that things were progressing on schedule.  As we 
approached the anticipated September issuance, calls to the agencies were 
conducted weekly and this was when I found out about the 1-4 month additional 
time which would be required for the permit issuance.  I dont know what else 
could have been done to track and alleviate problems encountered to ensure 
that the permits would be issued in a timely manner.