Re: GE LM-6000 purchase contract for Las Vegas Cogeneration II project

From
Kay Mann kay.mann@enron.com
To
Dale Rasmussen
Date
Fri, 30 Mar 2001 09:14:00 -0800 (PST)
We are trying to close with Delta, and they saw a March 20th draft.  Also, I 
had it  revised to take out E Next and substitute the llc.  So now I have two 
versions.  Just trying to get it clear.  I've spoken with Lee about revising 
the contract to pick up the new contract, leaving the "old" turbine in the 
master agreement, to be included in the LV Co Gen break out contract.

Couldn't be simpler.

Kay


   
	
	
	From:  Dale Rasmussen @ ECT                           03/30/2001 04:54 PM
	

To: Kay Mann/Corp/Enron@ENRON
cc:  

Subject: Re: GE LM-6000 purchase contract for Las Vegas Cogeneration II 
project  

The answer is yes-sort of.

The last thing I heard, 3 of the 4 current turbines are to go to Delta, with 
the 4th (August '01 delivery) to go to LV Cogen 2.

The real twist on this now will be the fact that we will need to somehow 
break the 4th turbine out from the contract.  At the same time, we have to 
confirm that the pricing (and related LD's, etc.) that would otherwise apply 
to the new turbines actually get assigned to the Delta turbines (in order to 
make our EPC contract for LV Cogen work right.

No headaches, eh?
Quoted or forwarded from earlier messages
Kay Mann@ENRON
03/29/2001 05:02 PM
To: Dale Rasmussen/HOU/ECT@ECT
cc:  
Subject: Re: GE LM-6000 purchase contract for Las Vegas Cogeneration II 
project  

Is this for the  turbines being sold to Delta as opposed to the new 
replacement equipment?

Thanks,

Kay



Dale Rasmussen@ECT
03/27/2001 01:19 PM
To: lee.johnson@ss.ps.ge.com, Bill Williams/PDX/ECT@ECT, Kay 
Mann/Corp/Enron@Enron, scofer@llgm.com, tconstan@llgm.com
cc: Jody Blackburn/PDX/ECT@ECT, Ed Clark/PDX/ECT@ECT 

Subject: GE LM-6000 purchase contract for Las Vegas Cogeneration II project

Bill Williams has confirmed that the attached version of the LVC-2 contract 
is the final form.  I have added a footer stamp identifying it as "Rev 5 - 
3/27/01".  Everything else is identical to the draft circulated March 12.


The second attachment is to be inserted as Exhibit H-2 in the contract.  

Thanks.