RE: Luzenac

From
Andrea Woodland andrea.woodland@enron.com
To
Hall, Steve C. (Legal), Sean Crandall, Diane Cutsforth
Date
Wed, 2 Jan 2002 19:46:14 -0800 (PST)
Doesn't the 10 NERC days mean we start delivering on Jan. 16th, not the 15th?
Quoted or forwarded from earlier messages
-----Original Message-----
From: 	Hall, Steve C. (Legal)  
Sent:	Monday, December 31, 2001 10:14 AM
To:	Crandall, Sean; Cutsforth, Diane
Cc:	Woodland, Andrea
Subject:	Luzenac

Luzenac has suspended its contract for 10 NERC business days, starting Jan. 1.  Therefore, we will not schedule power to Luzenac during this time, or charge Luzenac damages.

A "NERC Business Day" is any day except for a Saturday, Sunday, or NERC holiday.  By my calculations, this means that we will resume deliveries on January 15th.

Andrea, you might confirm with these guys that they agree with this calculation of days.---sch