co-op city; REVISED project schedule AND capex/o&m number updates.
- From
- Scott Laidlaw scott.laidlaw@enron.com
- To
- ray.danner@enron.com, allan.karels@enron.com, Mark Brand, Kay Mann, Robert Sevitz, peter.d'alessandro@enron.com, robin.long@enron.com, Randy Pais
- Date
- Thu, 15 Mar 2001 15:47:00 -0800 (PST)
1) re: revised project sched - plz see attached file. updated scheds for both gtgs and hrsgs based on conversations today with s&s, and nooter/deltak, respectively. for the gtgs, time period from order to ex-works is 17 months. for hrsgs, time period from order to ex-works is also 17 months. with "delay" in ordering major equipment until funds released in mid-nov01, the project's cod is delayed until april04; represents a worsening of the schedule by 10 months. 2) re: revised capex/o&m numbers. - by cob friday, 16mar01: - complete revised sched. status - attached. - complete scope reconciliation. status - completed with pb power's john mesko on thursday, 15mar01. - complete revised puts/takes to existing benchmark analysis, with 1 x lm2500 and 1 x lm6000, including detailed listing of assumptions. develop preliminary assessment of "cap." status - to complete fri am, 16mar01. - complete cash flow analysis. status - by mark brand. - by noon monday, 19mar01. - complete var assessment of model by mid morning at latest. status - by mark brand. - finalize "cap" level. status - pending. - provide filled in template to jeff ader for approval to send to pb power/co-op city. status - pending. - send info to pb power/co-op city by noon. status - pending. plz note that client has adjusted sched to allow 1 days review of data by co-op board before their formal meeting on tues, 20mar01. plz call with any questions. regards. scott.