MID C Question
- From
- Steven Luong steven.luong@enron.com
- To
- Lisa Gang
- Date
- Mon, 3 Jun 2002 12:16:28 -0700 (PDT)
Hi Lisa, I am working on a Hedging Activity Report that will be sent to E&Y on a weekly basis. I think Mo is out of the office so I heard that you might be the right person to ask for help. For the first week, I am using a spreadsheet that Mo sent where he bought some July power at MID C. It looks like the MID C power along with our NW Del length makes us flat for July at MID C and Montana System Border as well. My questions are: How does power flow between MID C and the other delivery points (like Montana)? Do we incur a transmission cost on top of what he bought the power for? We are actually a little long (960 MWh) b/c of the Air Products deal that is a little unique ... what happens to this length? If it's easier to explain over the phone, please give me a call at 713-853-4748. Thanks for your help. Steve