4 Mar 2002, 22:38 UTC
(no subject)
- From
- Mark Ferguson mark.ferguson@enron.com
- Bcc
- Jan Moore, Martha Janousek
- Date
- Mon, 4 Mar 2002 14:38:07 -0800 (PST)
Kim, Per Jan Moore's phone conversation this morning requesting the TW Capital IT project expenses for 2000 to Current: The RMS work orders show a total of $105,622 actually billed to TW. The budgeted amount was $690,510. The work orders never were allocated with the actual costs, so majority of the actual costs are still showing up on NNG's books. The Market Intelligence work order shows a total of $36,949 actually billed to TW. Let me know if we need to discuss this further. Thanks, Mark Ferguson Enron Transportation Services IT Manager (713) 853-3186