Interconnect Agreement

From
Gerald Nemec gerald.nemec@enron.com
To
Eric Gillaspie
Date
Mon, 24 Apr 2000 06:29:00 -0700 (PDT)

The sender added no text of their own; everything below is quoted or forwarded.

Quoted or forwarded from earlier messages
---------------------- Forwarded by Gerald Nemec/HOU/ECT on 04/24/2000 01:29 
PM ---------------------------


Robert D Morgan
04/18/2000 12:12 PM
To: Gerald Nemec/HOU/ECT@ECT
cc: Brian M Riley/HOU/ECT@ECT 
Subject: Interconnect Agreement

In the short-term, I need two agreements:

1)  A delivery point from LRC to SkyGen Energy LLC at the Cosmar plant in 
Ascension Parish, La.  Bridgeline Holdings will install, own, and operate 
5369' of 8" and the 100MM/D measurement station.  Next week would be okay.

2)  A bi-directional point between HPL and Tejas. The details are still being 
negotiated.  If possible, I would like it Wedesday EOB.

Item      Install  Own  Operate
 11mile of 16 Header     Tejas  Tejas  Tejas
 12 on 30 Hot Tap for Texoma   HPL  HPL  HPL
1600, of 16 between Texoma and M&R   Tejas  HPL  HPL
 Check Measurement (Flow Computer, SCADA)  Tejas  Tejas  Tejas
 OPP to protect HPL    Tejas  HPL  HPL
 Custody Measurement    Tejas  HPL  HPL
 Flow/Pressure Control    Tejas  HPL  HPL
 Over-Ride Control     Tejas  Tejas  Tejas
 Easement for Hot Tap    Tejas  HPL  HPL
 ROW for 1600'     Tejas  HPL  HPL
 Easement for Measurement    Tejas  HPL  HPL