15 Jun 2000, 11:10 UTC
FERC Gives Guardian Favorable Preliminary Determination
- From
- Lorna Brennan lorna.brennan@enron.com
- To
-
Bill Cordes, Julie McCoy, tim.aron@enron.com, Steve Klimesh, Sarabeth Smith, gary.sova@enron.com, Rob Wilson, Lon Stanton, kristen.hand@enron.com, Keith Petersen, Michele Winckowski, Donna Martens
and 97 more
Josie Call, bret.fritch@enron.com, Donald Vignaroli, Margaret Carson, roger.westfall@enron.com, Steve Thomas, doug.aschwege@enron.com, judy.beck@enron.com, ken.anderson@enron.com, Bryan Reinecke, Robert Johnson, carolyn.descoteaux@enron.com, becki.souci@enron.com, Gary Choquette, John Goodpasture, Michael Ratner, rockey.storie@enron.com, Kent Miller, John Dushinske, Dave Neubauer, Michael Bodnar, Joni Bollinger, david.badura@enron.com, Janet Bowers, Craig Buehler, Bob Burleson, allen.cohrs@enron.com, John Fiscus, Steve Gilbert, Morgan Gottsponer, james.harvey@enron.com, Stephen Herber, Dana Jones, stephanie.korbelik@enron.com, bill.mangels@enron.com, Penny McCarran, Vernon Mercaldo, Larry Pavlou, eileen.peebles@enron.com, tony.perry@enron.com, loren.penkava@enron.com, Ken Powers, Chris Sebesta, Frank Semin, neal.shaw@enron.com, Larry Swett, Kay Threet, mike.ullom@enron.com, lisa.valley@enron.com, Chuck Wilkinson, Jim Wiltfong, Jo Williams, karen.lagerstrom@enron.com, Ray Stelly, Bob Stevens, Sue Neville, Mike Barry, Martha Janousek, Kimberly Watson, Don Powell, Steve Weller, michael.stage@enron.com, Tim Johanson, laura.lantefield@enron.com, Frank Oldenhuis, Jeff Nielsen, tracy.schwartzkopf@enron.com, Robert Mason, Sean Bolks, miriam.martinez@enron.com, Lynn Blair, Rick Dietz, Steven January, Sheila Nacey, Dari Dornan, Maria Pavlou, Jim Talcott, Mary Kay Miller, Michel Nelson, Mike McGowan, Julia White, Drew Fossum, Glen Hass, Mary Darveaux, Rita Bianchi, Ranelle Paladino, Shelley Corman, Steven Harris, Jeffery Fawcett, Lorraine Lindberg, Kevin Hyatt, Christine Stokes, TK Lohman, Michele Lokay, Lindy Donoho, Lee Huber, Susan M Scott - Date
- Thu, 15 Jun 2000 04:10:00 -0700 (PDT)
FERC Gives High Sign to WI Pipe Competition
The northern Illinois and southeastern Wisconsin gas transportation
markets, which long have been dominated by
ANR Pipeline, moved one step closer to obtaining pipeline-on-pipeline
competition yesterday when FERC awarded
the proposed Guardian Pipeline LLC a favorable preliminary
determination on non-environmental issues.
The decision was a major win for the proposed greenfield pipeline
because not only did it shoot down most of the
arguments presented by ANR to thwart the project, but it found that
even though the project would "adversely
affect" landowner interests, Guardian was making "reasonable efforts"
to mitigate the impact on landowners.
Moreover, FERC ruled that while the $224 million pipeline would compete
head-to-head with ANR, it would not
have a negative affect on the Coastal pipeline and its customers. "On
balance, the Commission finds that the
proposed Guardian pipeline will provide substantial public benefits
with minimal adverse impacts," the order said
[CP00-36].
The Commission also found that sufficient need was established for the
36-inch, 140-mile pipeline that would
transport 750,000 Dth/d of gas from the Chicago Hub to markets in
northern Illinois and southern Wisconsin,
providing customers there with an alternative to ANR and access to
competitive Canadian gas supplies. It would
terminate near Ixonia, WI, where it would interconnect with Wisconsin
Gas Co.'s distribution system. At the
Chicago Hub, the pipeline proposes to interconnect to Alliance
Pipeline, Northern Border Pipeline, Midwestern Gas
Pipeline and Natural Gas Pipeline Co. of America.
Guardian has executed 10-year precedent agreements with four shippers
for 702,500 Dth/d, which equals about
94% of the project's design capacity. The largest shipper by far will
be Wisconsin Gas, which has committed itself
to 650,000 Dth/d of the capacity on the proposed line. In fact, the
Guardian project is an outgrowth of Wisconsin
Gas's request for proposals (RFP) process in June 1998, which the LDC
initiated in anticipation of the expiration of
its firm transportation contract with ANR in October 2003. The other
shippers on Guardian include Alliant Energy
(10,000 Dth/d), WPS Energy Services Inc. (2,500 Dth/d) and an unnamed
shipper (40,000 Dth/d). The project has a
targeted in-service date of Nov. 1, 2002.
In multiple protests filed at the Commission, ANR argued that
Guardian's application was "patently deficient"
because it didn't include the proposed lateral that Wisconsin Gas plans
to build to interconnect with Guardian.
Wisconsin Gas currently is seeking the approval of state regulators to
build the lateral. Furthermore, ANR claimed
Wisconsin Gas was using its monopoly power as a franchised LDC serving
southern Wisconsin to subsidize the
Guardian project. Wisconsin Gas's parent, WICOR Inc., is one of the
sponsors of Guardian. The other backers are
CMS Gas Transmission and Storage and Viking Gas Transmission.
But FERC rejected both arguments. "While previous attempts to inject
competition into ANR's market in this area
have failed, we believe that this area is ripe for competition, and
that it is only a matter of time before other
pipelines submit similar proposals to the Commission. We find that the
proposed project will provide southeastern
Wisconsin with access to another source of supply, which will allow
this market to enjoy the benefits of
pipeline-to-pipeline competition for the first time," the order noted.