FW: preliminary report

From
Franson, Rob" @ENRON rfranson@czn.com
To
Darrell Schoolcraft
Date
Thu, 13 Dec 2001 07:56:55 -0800 (PST)
Attached is a copy of the preliminary report that  recommends that the inlet pressure to Citizens "Griffith Plant" Station be  limited to 740 psig.  Note that this is only a preliminary report that  Citizens is reviewing.  Some of our "reviewers" are on vacation, and have  held up the process of getting this report finalized.
 
Since  I was temporarily assigned to another position during the time that gas was  introduced to this line, I have asked my employee Martin Conboy to create a log  of events on how these stations had been operated.  I will send it to you  later today.  
 
Can  you have David Roensch review to see if anything is missing.  I feel that  it is a good idea to document the different operation modes with results prior  to agreeing on any further changes.
Quoted or forwarded from earlier messages
-----Original Message-----
From: Ray Kelm - Kelm Engineering  [mailto:ray@kelm-engr.com]
Sent: Wednesday, November 28, 2001 3:22  PM
To: Robert Franson - Citizens
Subject: preliminary  report
Robert,
 
I had to delete a couple figures to get the size  below 1 meg to email.
 
Call if you have questions.
 
Ray
 - CZN102301mod.doc