Weekly Activity Report

From
Larry Campbell larry.campbell@enron.com
To
Rick Loveless
Cc
marcy.warming@enron.com
Bcc
marcy.warming@enron.com
Date
Wed, 11 Aug 1999 07:26:00 -0700 (PDT)
Presented Title V training to the Flagstaff Team.  The training included 
responsibilities, recordkeeping and semi annual reporting requirements.

A meeting was held with representatives of Transwestern and PG&E to discuss 
activities related to removing PCB's from the Topock Lateral.  Sampling data 
was reviewed and discussions were held addressing past cleaning efforts.  
PG&E has stated by letter and verbally that natural gas volumes will be 
decreased weekly until PCB concentrations fall below 5 ppm.  Transwestern 
will be implementing a pipeline cleaning of the remaining 1850 of pipe 
between our M/S and the PG&E C/S.  Included in this cleaning will be 
decontamination of the additional filter separators and meter runs.

Assisted in the compilation and data gathering of the Title V compliance 
monitoring and annual certification reports for C/S No. 5, Thoreau.

The annual blanket request for the Arizona SHPO was submtted for renewal.

Notification letters were submitted to the state of New Mexico notifiying the 
agency of like for like replacements of recipricating engines at the AToka 
No. 1 C/S.  Additional notifications were submitted to the agency apprising 
them of engine removal activities at C/S's No. 5 and 9 which would impact 
emissions fees.