Listed below are the issues, pretty much as written, in the meeting on the West Texas Leg.  Some are self-explanatory while others are somewhat cryptic.  I will follow up with a list that better defines each issue, and you might have your guys think about each as well.  We'll get back together soon (I'm not sure I can do it this week), and discuss an action plan.

-	CS 9 fuel
-	Atoka Lateral 	We have both supply and market opportunities within the lateral itself
-	Turbocharge the Atoka #3 units
-	Look at Zia pressure obligation on the contract
-	Agave replacement gas at Atoka #3
-	Complete the loop between WT-1 and WT-2
-	Coolers to WT-2
-	Pecos compressor re-wheel and engine upgrade
-	200 	300 (WT-2 to Pecos) flow study
-	Look at Block Valve 16 bi-directional interconnect w/Sid Richardson, and ability flow incremental above 340 on the total system
-	Look at Keystone into NNG; back to TW south of WT-2
-	Check pressure of Stations 6 & 7, and PNM receipts
-	MAOP restriction on Panhandle leg due to encroachment