Enron email

Algorithmic Indexing

8 Mar 2001, 11:42 UTC

weekly environmental activity report-Roswell Area

From
Larry Campbell larry.campbell@enron.com
To
gary.fuller@enron.com, Rick Loveless, Mike Riedel, Butch Russell
Date
Thu, 8 Mar 2001 03:42:00 -0800 (PST)
A meeting has been scheduled on 3/16 with the California Fish and Game to 
discuss the following issues:  1)presentaiton of the 1999 and 2000 annual 
reports which are required by the facility's 2081 permit. 2) developing an 
agreement with F&G as to how the 41 acre credits held by EOTT will be managed 
to ensure compliance with requirements of the F&G. 3) Presentation of the 
results relating to surveys conducted in the path of construction for the 
Rogas project.

The waiver to lay pipeline above ground for the Rogas constsruction was 
approved by the Offfice of the State Fire Marshall, Pipeline Safety 
Division.  There were 8 city, county, state and federal agencies notified by 
application for approval to construct the 9 mile pipline system consisting of 
3 piplines.  This is the only agency approval received as yet.

Acre credits were obtained from Aera for the construction of the Rogas 
pipeline.  Aera is an oil company with major holdings of acreage available 
for purchase.  It was felt that due to the time constraints for initiating 
this project and the concern with not receiving the credits from the F&G that 
EOTT would purchase Aera credits to ensure procurement of the necessary 
acreage for the Rogas project.  This is a major plus for the project.

The rough draft of the baseline noise survey for the turbine installations in 
Az. was received.  Some changes will be made in each document.,  as the 
contractor has made some obvious conclusions and asumptions which are not 
valid or representative of the mitigation Transwetern will do.  The Navajo 
Nation has requested that an onsite survey be conducted at the C/S on the 
reservation (C/S 3 and 4)  for T&E plants and animals and archeology.  A 
contractor has been notified and surveys will be completed by 3/12. The F-1 
environmental report  for the FERC application will be submitted to Donna by 
this friday.   

The air permit applications for C/S 1 and 2 have been started.   A meeting 
with EPA in San Francisco has abeen set to discuss permitting the C/S 
facilities on the reservation on 3/20.  After the meeting, applications 
should be in front of the Navajo air permitting agency and the EPA within a 
week. Air permits are expected  within 5-7 months after submittal of the 
application.  During a conference call this week, a proposal was submitted to 
remove the existing auxillary generators and replace with 2 units at each 
location.  This will delay submittal of the air applications 3-4 days, 
assuming no major issues result.  One interesting issue that might develop is 
that one of the generators might possibly be a wind turbine.