2000 Goals and Objectives
- From
- Michael Moran michael.moran@enron.com
- To
- Rod Hayslett
- Date
- Tue, 28 Nov 2000 01:42:00 -0800 (PST)
Rod, here is my input on the 2000 Goals and Objectives. My numbering will
correspond to the list of goals and objectives which accompanied your e-mail.
1. Completed. Final certificate was gotten in Feb. 2000 and the west leg
construction was completed and in service around 10/1.
2. Partially completed. PD received on Phase 5 on 11/21 but the EIS is
not expected til 1/01.
3. No input.
4. No input.
5. Completed.
6. As you know, CitrusNet was not completed. We have developed a good
structure for the transaction being considered a sale and we have developed
the necessary contract documents to accomplish the deal but at present we
have no takers.
7. No comments.
8. I think this was intended to be the MOPS sale which I believe has been
moved to next year.
9. No comment.
10. Efforts were made with a couple of potential buyers to work out a
deal but nothing definitive was accomplished.
11. A lot of work was done in connection with Project Cristobal but
nothing was finalized with potential partners.
12. No comment.