19 Jan 2001, 09:17 UTC
RE: TVA' s Bid
- From
- Stuart L. Goza slgoza@tva.gov
- Date
- Fri, 19 Jan 2001 01:17:00 -0800 (PST)
I assume that a 95% availability for all months, with only the major maintenance outages excluded, and LD energy would bring the value up to the $6.50/kw-month, but I have not requested an analysis of this type product. If you think that would work for Enron, I will ask for the analysis and provide a bid for that product.
Quoted or forwarded from earlier messages
> ---------- > From: Rogers.Herndon@enron.com[SMTP:Rogers.Herndon@enron.com] > Sent: Friday, January 19, 2001 7:04 AM > To: Goza, Stuart L. > Cc: Kevin.M.Presto@enron.com > Subject: RE: TVA' s Bid > > > Stuart - > > Does TVA have a counter-proposal that would increaase the value to EPMI's > original offer? > > Rogers Herndon >