Longview DASH Request

From
Chip Schneider chip.schneider@enron.com
To
Louise Kitchen
Cc
Christopher F. Calger
Bcc
Christopher F. Calger
Date
Mon, 29 Oct 2001 17:26:16 -0800 (PST)
Louise:

A termination of equipment associated with the Longview project on or before 10/31/01 will require Enron to write-off approximately $23 million, not inclusive of approximately $3 million in development costs to date.
To extend orders for equipment to 11/30/01 will cost an additional $5.3 million in cancellation charges.
To extend orders for equipment to 12/31/01 will cost an additional $8.7 million (inclusive of the $5.3 million above, therefore, net $3.4 million) in cancellation charges.

Termination at any time between now and year-end 2001 provides no material recovery potential for money spent.

Regards,

Chip Schneider
713-853-1789