22 Oct 2001, 18:52 UTC
RE: Acquisition Projects
- From
- Tracy Geaccone tracy.geaccone@enron.com
- To
- Judy Lin
- Date
- Mon, 22 Oct 2001 11:52:02 -0700 (PDT)
Should be expensed in the 4th Q
Quoted or forwarded from earlier messages
-----Original Message-----
From: Lin, Judy
Sent: Monday, October 22, 2001 1:46 PM
To: Geaccone, Tracy
Cc: Ratner, Michael; Lev, Jennifer
Subject: Acquisition Projects
I've been requested by Rod and John Goodpasture to set up the following acquisition projects in 2000 under
Co. 0366's book:
Project # Project Name Project-to-Date
C.005532 Reliant Acquistition $21,173.59
C.005535 LG & E Asset Acquisition 7,128.54
C.005539 Kansas P/L Prohect 7,173.43
C.005542 Hugoton-Bushton 54,401.40
C.005543 Destin P/L, Sea Robin 13,996.76
C.005544 Phosphate Slurry P/L 24,131.30
--------------------------------------------------------------------------------------
Total $128,005.02
==========
As the projects have been completed, may we allocate the costs ? to whom ?
Please advise.
Judy 3-7193