12 Sep 2001, 23:24 UTC
FW: Outage Coordination Commercial Review (NNG & TW)
- From
- Kimberly Watson kimberly.watson@enron.com
- Date
- Wed, 12 Sep 2001 16:24:58 -0700 (PDT)
Mark, FYI on the outage meeting Thursday. Kim.
Quoted or forwarded from earlier messages
-----Original Message-----
From: Graves, Jerry
Sent: Wednesday, September 12, 2001 5:46 PM
To: Graves, Jerry; Alexander, James C.; Blair, Lynn; Bonnstetter, Mike; Boothe, David; Boston, Jerry; Brown, Sharon; Bryant, Mike; Buchanan, John; Burns, Christopher; Clark, Scott; Cordes, Bill; Corless, Gary; Corman, Shelley; Geaccone, Tracy; Gilbert, Tom; Good, Chuck; Gottsponer, Morgan; Graham, Charlie; Harris, Steven; Hood, Colleen; Howard, Randy; January, Steven; Jolly, Rich; Jordan, Fred; Keller, John R.; Kowalke, Terry; Kudym, Judy; Kuehl, Toby; Lawrence, James; LeBeau, Randy; Lowry, Phil; Maestas, Gary; Mall, Greg; Martens, Donna; McGillivray, RR; Mertz, Tom; Moore, Jan; Morse, Ronnie; Nelson, Mike; Neubauer, Dave; Odneal, Dave; Rice, Randy; Roensch, David; Schoolcraft, Darrell; Schroeder, Jim; Smith, Rick; Spraggins, Gary; Stephens, LD; Swett, Larry; Thomas, Steve; Watson, Kimberly; Williams, Jo; Williams, Walt; Abdmoulaie, Mansoor; Alters, Dennis; Dushinske, Adam; Faucheaux, Eric; Frazier, Perry; Gilbert, Maurice; Hughes, Matt; Matthews, Ron; Ramsaran, Gale; Smith, Buzz; Anderson, Ken; Aschwege, Doug; Beck, Judy; Descoteaux, Carolyn; Dobbins, Dan; Johnson, Robert L.; Kolarik, David; Reinecke, Bryan; Sans Souci, Becki; Westfall, Roger; Asante, Ben; Choquette, Gary; Kouri, Kim; McChane, Bob; Sturn, John; Wirasinghe, Errol
Subject: Outage Coordination Commercial Review (NNG & TW)
FYI,
Please take note of the date change.
The next Outage Coordination Commercial Review meeting is 09/13/01. The purpose for the meeting is to discuss outages that have a flow impact with the Commercial groups. If you have any questions or concerns, please give me a call.
Jerry Graves
713-345-8923
When: Sept. 13
Time: 1:00 to 2:00
Where: Houston 49C2
Omaha VCR - 7th floor
Field Personnel - Conference # 877-795-3687
Code # 755555
Northern Border Pipeline
Location Date Scope Comments
CS08 09/16/01 to 09/16/01 MP2, and replace thermocouple. (10 hrs) Potential impact is low.
CS04 09/13/01 to 09/13/01 Scope, MP2, Emissions testing. (10 hrs) Potential impact is low.
CS07 09/18/01 to 09/18/01 Scope, Wash, MP2, and replace Argotech pump. (10 hrs) Potential impact is low.
CS09 09/25/01 to 09/25/01 Scope, MP2, Clean oil coolers. (10 hrs) Potential impact is low.
CS10 09/27/01 to 09/27/01 Scope, Wash, MP2, and replace their inlet air pre-filters. (10 hrs) Potential impact is low.
CS12 10/04/01 to 10/04/01 Scope, Wash, MP2, and valve mods. (10 hrs) Potential impact is low.
CS03 10/16/01 to 10/16/01 Wash, MP2, and replace their inlet air filters. (10 hrs) Potential impact is low.