Mark, FYI on the outage meeting Thursday.

Kim.
Quoted or forwarded from earlier messages
-----Original Message-----
From: 	Graves, Jerry  
Sent:	Wednesday, September 12, 2001 5:46 PM
To:	Graves, Jerry; Alexander, James C.; Blair, Lynn; Bonnstetter, Mike; Boothe, David; Boston, Jerry; Brown, Sharon; Bryant, Mike; Buchanan, John; Burns, Christopher; Clark, Scott; Cordes, Bill; Corless, Gary; Corman, Shelley; Geaccone, Tracy; Gilbert, Tom; Good, Chuck; Gottsponer, Morgan; Graham, Charlie; Harris, Steven; Hood, Colleen; Howard, Randy; January, Steven; Jolly, Rich; Jordan, Fred; Keller, John R.; Kowalke, Terry; Kudym, Judy; Kuehl, Toby; Lawrence, James; LeBeau, Randy; Lowry, Phil; Maestas, Gary; Mall, Greg; Martens, Donna; McGillivray, RR; Mertz, Tom; Moore, Jan; Morse, Ronnie; Nelson, Mike; Neubauer, Dave; Odneal, Dave; Rice, Randy; Roensch, David; Schoolcraft, Darrell; Schroeder, Jim; Smith, Rick; Spraggins, Gary; Stephens, LD; Swett, Larry; Thomas, Steve; Watson, Kimberly; Williams, Jo; Williams, Walt; Abdmoulaie, Mansoor; Alters, Dennis; Dushinske, Adam; Faucheaux, Eric; Frazier, Perry; Gilbert, Maurice; Hughes, Matt; Matthews, Ron; Ramsaran, Gale; Smith, Buzz; Anderson, Ken; Aschwege, Doug; Beck, Judy; Descoteaux, Carolyn; Dobbins, Dan; Johnson, Robert L.; Kolarik, David; Reinecke, Bryan; Sans Souci, Becki; Westfall, Roger; Asante, Ben; Choquette, Gary; Kouri, Kim; McChane, Bob; Sturn, John; Wirasinghe, Errol
Subject:	 Outage Coordination Commercial Review (NNG & TW)


FYI,

Please take note of the date change. 

The next Outage Coordination Commercial Review meeting is 09/13/01.  The purpose for the meeting is to discuss outages that have a flow impact with the Commercial groups. If you have any questions or concerns, please give me a call.  


Jerry Graves 
713-345-8923


When: Sept. 13
Time: 1:00 to 2:00
Where: Houston 49C2
             Omaha  VCR - 7th floor
             Field Personnel - Conference # 877-795-3687  
                                         Code # 755555

                                                                                                              
Northern Border Pipeline
 Location	Date  	Scope 	Comments	
				
CS08	09/16/01 to 09/16/01	MP2, and replace thermocouple. (10 hrs)	Potential impact is low.	
CS04	09/13/01 to 09/13/01	Scope, MP2, Emissions testing. (10 hrs)	Potential impact is low.	
CS07	09/18/01 to 09/18/01	Scope, Wash, MP2, and replace Argotech pump. (10 hrs)	Potential impact is low.	
CS09	09/25/01 to 09/25/01	Scope, MP2, Clean oil coolers. (10 hrs)	Potential impact is low.	
CS10	09/27/01 to 09/27/01	Scope, Wash, MP2,  and replace their inlet air pre-filters. (10 hrs)	Potential impact is low.	
CS12	10/04/01 to 10/04/01	Scope, Wash, MP2,  and valve mods. (10 hrs)	Potential impact is low.	
CS03	10/16/01 to 10/16/01	 Wash, MP2, and replace their inlet air filters. (10 hrs)	Potential impact is low.