18 Oct 2001, 15:20 UTC
Sublette #26
- From
- Jerry Graves jerry.graves@enron.com
- Date
- Thu, 18 Oct 2001 08:20:28 -0700 (PDT)
FYI, Per Mike Burnam, and Chuck Good unit 26 needs to be overhauled. They will start on it 10/22/01 and the estimated completion date is 12/17/01. (8 weeks) Unit 27 is running fine at present time so there is know flow impact. Keep your fingers crossed. Jerry