29 Aug 2001, 18:48 UTC
Month End Close Schedule *REVISED*
- From
- Richard Pinion richard.pinion@enron.com
- To
- Lisa Kinsey, Victor Lamadrid, Daren J. Farmer, George F. Smith, Patti Sullivan, Theresa Staab, Mark L. Schrab, Sabra L. Dinari, Clarissa Garcia, Gerald Gilbert
- Cc
- Tammy Jaquet, Shahnaz Lakho, Robert Superty, Bob M Hall, Matt Pena, Brian Ripley, Kathryn Bussell
- Bcc
- Tammy Jaquet, Shahnaz Lakho, Robert Superty, Bob M Hall, Matt Pena, Brian Ripley, Kathryn Bussell
- Date
- Wed, 29 Aug 2001 11:48:25 -0700 (PDT)
Changes are in blue. Last month there was some confusion from several schedulers I spoke to about when changes could be made to (August) after the cut off: As noted in the table, after Friday, August 31st at 6PM there can be no changes (i.e. re-nominate, re-track, re-balance, bridge back to Sitara etc.) made to August production until Wednesday morning, September 5th. At 6PM Friday (or before if you are ready) I will be by to pick up the reports and exceptions dialogue. thx RP