4 Dec 2000, 16:46 UTC
New Rockies
- From
- Paul T Lucci paul.lucci@enron.com
- Date
- Mon, 4 Dec 2000 08:46:00 -0800 (PST)
Here are the pipeline expansions within or out of the Rockies: Pipeline Capacity In Service Date Delivery Region CIG 50,000Dth/d Fall 2001 Mid Continent Trail Blazer 150,000Dth/d Fall 2002 Mid Continent WIC Med. Bow 500,000Dth/d Fall 2001 Rockies (Cheyenne Hub) Kern River 125,000 Dth/d Summer 2002 So Cal Border Pipeline Expansions Currently in Open Season Pipeline Capacity In Service Date Delivery Region Coastal Connection 540,000 Dth/d Fall 2003 Mid Continent Williams 540,000 Dth/d Fall 2003 Mid Continent Northern Border 340,000 Dth/d Fall 2003 Mid Continent via Northern Border All these proposed pipelines currently have no firm contractual commitments, we believe only one project will be built and that the true in-service date is sometime in 2004. It takes 36 months from start to finish, for these green field projects.