Enron email

Algorithmic Indexing

1 Aug 2001, 00:41 UTC

GTV project status weekly update

From
Zhiyong Wei zhiyong.wei@enron.com
To
Louise Kitchen, Geoff Storey, Mark Pickering, Beth Perlman, Stephen Stock
Date
Tue, 31 Jul 2001 17:41:02 -0700 (PDT)
Please find below the weekly project status update for GTV and the attached file for the updated project timelines. Changes are underlined.

GTV status meeting attendees:  Zhiyong Wei, Jeremy Wong, Nayan Dattani, Bill Fortney, Karima Husain, Thu Dang, Chuck Ames, Geoff Storey, Jay Krish, Russ Severson, George Grant, Mike Swaim.

Accomplishments:
?	Incorporating physical deal positions in TDS:
o	Changes for the view aggregation have been completed.
o	Expandable Total in Cash Position has been completed.
?	Single point of deal entry for term deals:
o	Released to production.
?	Gas Daily deals:
o	Released to production.
?	Live feeds for Gas Daily/intra-month curves:
o	Released to production.
?	Saving different views in TDS:
o	Completed.
?	Capability for desk roll-ups on an ad hoc basis (phase 2, on hold since 7/9/01):
o	New process for roll-up aggregators has been completed.
?	Option Grid (phase 2):
o	Released to production.
?	Gas Daily options (phase 2):
o	Released to production.
?	Basis Options (phase 2):
o	Development of deal entry type for Basis Options has been completed in TAGG.
o	Development of loading correlation curves has been completed.
o	Changes to the Translator have been completed.
?	Transport Deal Capture & Valuation (phase 2):
o	Creation of new deal entry type & database changes has been completed.
o	Changes to the Translator have been completed.
?	Add more information to the drill-down deal details.
o	Development has been completed.
?	New Flexible Deal Viewer.
o	Database schema design has been completed.

Plans for the week ending 08/03/01:
?	Continue User acceptance test of physical deal positions in TDS (Phase I items).
?	Continue IT development of Phase II issues.
o	Change PortCalc to value basis options.
o	Option reports (PL reports).
?	Add more information to the drill-down deal details.
o	User Acceptance Testing.
?	New Flexible Deal Viewer.
o	Continue GUI development.
o	Continue development of Query Engine.
o	Start working on loading data and related items.

Issues:
?	None.

Notes
?	Since Calgary office has not yet implemented the new GDI calc, there was a double counting issue with Canadian Gas Daily books last Friday, July 27. The IT team has been working closely with Calgary office to fix the problem as soon as possible.
?	In the last couple of weeks, a developer took a week and half off due to a family emergency and another developer took paternity leave for a week, which affected our project delivery timelines.


 

Thanks

Zhiyong