13 Dec 2000, 14:07 UTC
PJM RTO Filing/ PJM Answer to Motion for Defer the FERC ruling on RTO Status until 1/15/2001
- From
- Thane Twiggs thane.twiggs@enron.com
- To
- jeffery.ader@enron.com, Mark Bernstein, Scott Healy, Janelle Scheuer, tom.dutta@enron.com, Dana Davis, Paul J Broderick, Chris Dorland, Gautam Gupta, Michael R Brown, John Llodra, George Wood
- Date
- Wed, 13 Dec 2000 06:07:00 -0800 (PST)
Answer of PJM Interconnection, LLC., to Motion of New England Public Power Systems for Deferral of decision until January 15, 2001. At issue is whether a ruling by the FERC on the merits of PJM as an RTO may set an unfair precident that may affect other regional RTO filings. In their answer PJM asks that the FERC not delay action as requested by NEPPS and argues that the fact that a decision may be precedential clearly is not a basis for withholding a decision. PJM adds that Commission guidance as a precedent would in fact, be beneficial to RTO development. PJM is also concerned that a delay would affect the creation of PJM West with Allegheny Power since a deferal until January 15, 2001 may affect the negotiations and implementation.