Enron email

Algorithmic Indexing

30 Jul 2001, 22:14 UTC

Neptune Project order (ER01-2099)

From
Susan Scott susan.scott@enron.com
To
Tom Hoatson, Dan Staines, Daniel Allegretti, Howard Fromer, Chris Booth, Kathleen Carnahan, Scott Churbock, Mathew Gimble, Raimund Grube, sharon.hausinger@enron.com, zachary.inman@enron.com, Ben Jacoby
and 38 more Jeffrey Keenan, Dave Kellermeyer, Greg Krause, Steven Krimsky, Heather Kroll, Fred Mitro, john.moore@enron.com, Ron Tapscott, Rebecca Walker, rick.whitaker@enron.com, jeff.ader@enron.com, Mark Bernstein, Paul J. Broderick, Michael R Brown, Lisa Burnett, Larry F. Campbell, Dana Davis, Chris Dorland, tom.dutta@enron.com, Gerald Gilbert, joe.gordon@enron.com, david.guillaume@enron.com, Gautam Gupta, Scott Healy, John Llodra, posey.martinez@enron.com, Tom May, Jeffrey Miller, Narsimha Misra, ricardo.perez@enron.com, shelley.plauche@enron.com, Joe Quenet, Janelle Scheuer, Robert Stalford, Joe Stepenovitch, n..stewart@enron.com, Paul D. Thomas, George Wood
Cc
Donna Fulton, Christi L Nicolay, Sarah Novosel, James D. Steffes
Bcc
Donna Fulton, Christi L Nicolay, Sarah Novosel, James D. Steffes
Date
Mon, 30 Jul 2001 15:14:38 -0700 (PDT)
	On July 26, 2001, FERC issued an order conditionally approving the proposed tariff for the Neptune Project, which will consist of several thousand miles of undersea high-voltage direct current transmission systems connecting Main, New Brunswick and Nova Scotia to the capacity-constrained markets of Maine, New York City, Long Island and Connecticut.  As a merchant transmission facility, Neptune proposed to assume all the risk of the the project.  It proposed rates effectively capped by market forces.

	Conditions on the Commission's approval:  

		- Neptune must join an RTO adjacent to or containing the geographic area of its proposed faciliteis and must place operational control of its facilities under the RTO.

		- Service must be provided pursuant to the Order No 888 pro forma tariff (Commission denied Neptune's request for a waiver).

		- Neptune cannot negotiate bilateral transactions prior to conducting its open season; it must make all capacity available solely through the open season process.

If you would like any further information, please let me know.

Susan Scott Lindberg