Enron email

Algorithmic Indexing

14 Nov 2001, 14:09 UTC

Outage Commericial Review Meeting (NNG,TW, & NBPL)

From
Jerry Graves jerry.graves@enron.com
To
c..alexander@enron.com, Lynn Blair, mike.bonnstetter@enron.com, david.boothe@enron.com, jerry.boston@enron.com, Sharon Brown, Mike Bryant, John Buchanan, christopher.burns@enron.com, scott.clark@enron.com, Bill Cordes, gary.corless@enron.com
and 66 more Shelley Corman, Tracy Geaccone, Tom Gilbert, chuck.good@enron.com, Morgan Gottsponer, Charlie Graham, Jerry Graves, Steven Harris, Colleen Hood, randy.howard@enron.com, Steve January, Rich Jolly, fred.jordan@enron.com, John R. Keller, Terry Kowalke, Judy Kudym, Toby Kuehl, James R Lawrence, Randy LeBeau, Phil Lowry, Gary Maestas, greg.mall@enron.com, Donna Martens, rr.mcgillivray@enron.com, Jan Moore, Ronnie Morse, Mike Nelson, Dave Neubauer, Dave Odneal, Randy Rice, David Roensch, Darrell Schoolcraft, jim.schroeder@enron.com, Rick Smith, Gary Spraggins, LD Stephens, Larry Swett, Steve Thomas, Kimberly Watson, Jo Williams, Walt Williams, Mansoor Abdmoulaie, Dennis Alters, adam.dushinske@enron.com, Eric Faucheaux, Perry Frazier, Maurice Gilbert, Matt.Hughes@enron.com, Ron Matthews, gale.ramsaran@enron.com, Buzz Smith, ken.anderson@enron.com, doug.aschwege@enron.com, judy.beck@enron.com, carolyn.descoteaux@enron.com, dan.dobbins@enron.com, David L. Johnson, david.kolarik@enron.com, Bryan Reinecke, becki.sans@enron.com, roger.westfall@enron.com, Ben Asante, Gary Choquette, bob.mcchane@enron.com, John Sturn, errol.wirasinghe@enron.com
Date
Wed, 14 Nov 2001 06:09:20 -0800 (PST)
FYI,

The next Outage Coordination Commercial Review meeting is 11/14/01.  The purpose for the meeting is to discuss outages that have a flow impact for the month of December. Please review the attached outage report. If you have any questions, please give me a call.  

 

Jerry Graves 
713-345-8923

When: November 14
Time: 1:00 to 2:00
Where: Houston 49C2
             Omaha  VCR - 7th floor
             Field - Conference # 877-795-3687  
                        Code # 755555


NORTHERN BORDER PIPELINE	
	 	 	 	 	
 	Location	Date	Scope	Comments	
NB	CS11	12/03/01 to 12/03/01	 Scope/Wash, MP2, and Cooler mods.(10 hrs)	Potential impact is low.	
NB	CS07	12/13/01 to 12/13/01	 Maintenance/Wash, MP2, and Cooler mods.          (10 hrs)	Potential impact is low.	
NB	CS03	12/11/01 to 12/11/01	 Wash, MP2, (10 hrs)	Potential impact is low.