5 Jul 2000, 07:41 UTC
Various
- From
- Kay Chapman kay.chapman@enron.com
- Date
- Wed, 5 Jul 2000 00:41:00 -0700 (PDT)
Max, congrats on the Decero PPA - we need to wrestle up another 100 to 200 MW. This should be a priority given the profit potential of this deal as per Oz and Doug (+50M in 2000). Is there an ability to let Sabine or Irvin run with Vitro and get your attention on this item asap. I know that the Monterrey project is eating into your time. Do we need to augment your resources? On a different note, the current Monterrey control budget is showing a $5.3M negative variance from the original control budget. Is this accurate? Does this reduce the profitability or is it absorbed by the PPA's? Regards Delainey