Annual Certifications Reports Required by Title V

From
Larry Campbell larry.campbell@enron.com
To
team.big-lake@enron.com, Team Eunice-Kermit, team.kermit-wt2@enron.com, team.kermitturbine@enron.com
Cc
scott.clark@enron.com, Bob Bandel, James R Lawrence, robert.newman@enron.com, randall.mobley@enron.com
Bcc
scott.clark@enron.com, Bob Bandel, James R Lawrence, robert.newman@enron.com, randall.mobley@enron.com
Date
Mon, 2 Jul 2001 05:17:00 -0700 (PDT)
Be advised that there will be a meeting on Thursday 11:00 am August 23 at the 
NNG Turbine station, south of Kermit Tx.  to complete and submit annual 
certification reports which are required by the following Title V permitted 
facilities:

Seminole
Brownfield
Plainview

Spraberry

Irion Co. No. 1
Reagan Co. 2
Eldorado

Wt-2
Walton
Keystone

Kermit Turbine

Should a team decide not to attend this meeting, be advised that the required 
submittal date for the annual certifications for the state of Texas is 
September 8, 2001.  It will be your teams responsibility to ensure that the 
certifications are submitted prior to the 9/8/01 deadline should you decide 
not to attend the August 23 meeting.