6 Nov 2001, 16:10 UTC
Frontera Availability for tomorrow
- From
- John M. Forney m..forney@enron.com
- To
- Joe Capasso, Smith L. Day, Joe Errigo, George Phillips, iz.wong@enron.com, Alexander McElreath, Jeffrey Miller, Steve Olinde, Eric Saibi
- Date
- Tue, 6 Nov 2001 08:10:41 -0800 (PST)
Frontera is not scheduled to run tomorrow. However all units should be available, but offline with the following exception: He 10 - some gas line work is being done and Frontera can only run in a 1/1 config, meaninig a max of 220. The steamer, #3 and CT #1 will be the only units available. For this hour. Late word: If Ercot doesnt OOM us, the entire plant will be unavailable and offline for he 1, as well. In this scenario, only hour ending 1 and 10 would be affected. Any questions? JMF