21 Jun 2000, 11:18 UTC
May O&M Variance questions
- From
- Jon Trevelise jon.trevelise@enron.com
- Date
- Wed, 21 Jun 2000 04:18:00 -0700 (PDT)
The sender added no text of their own; everything below is quoted or forwarded.
Quoted or forwarded from earlier messages
----- Forwarded by Jon Trevelise/Houston/Eott on 06/21/00 11:29 AM -----
John Berry
06/20/00 07:05 PM
To: Jon Trevelise/Houston/Eott@Eott
cc: Alan Shropshire/Houston/Eott@Eott, Lori Maddox/Houston/Eott@Eott
Subject: May O&M Variance questions
Jon,
Following up your two questions this morning, we obtained the following info
from pulling invoices and phone inquiries.
Temp & Contract - Systems Fees ($28) variance
Variance attributable to RC 9701 - Systems Software which budgeted $6.7 and
incurred $34.8 for consulting services and contract support. Discussed with
Steve Findley. The invoices are summarized as follows:
McCorquadale Consulting - $8.2 for commercial maps and web support.
Indu Kilambi Consulting - $5.1 for general systems support
Idea Integration - $8.6 for commercial maps and
documentation preparation
Comsys Consulting - $12.9 for FoxPro position reporting issues
$34.8
Major Expense Jobs - Crane System ($106) variance
Variance attributable to RC 7354 - TXNM Crane System which budgeted -0- and
incurred $105.6. Discussed with Gary Wright and Fixed Assets accounting,
waiting on answer from Bobby Garduno.
Review of invoices revealed that only $24 related to Crane Flood (Albritton
Machine, Inc. for pump repair and reconditioning). Garduno to provide
description of flood. Balance of $81.6 related to cleaning and work on Ozona
Tank #1339. Apparently an AFE has been prepared for the Ozona Tank work, but
the AFE has not been approved. If the AFE is approved, these costs will be
capitalized.