long-term PJM tolling opportunity

From
John Llodra john.llodra@enron.com
To
Dana Davis, Robert Benson, chris.calger@enron.com, Kevin M. Presto, Frank Vickers, Craig Taylor
Cc
George Wood
Bcc
George Wood
Date
Thu, 28 Feb 2002 13:47:29 -0800 (PST)
All

Learned of an opp today for a L.T. physical toll on a peaking plant in PJM.  Probably way too early for this, but we may be able to follow this one and act when we're further along.  Here are the details:

Plant is being developed by PPL - consists of 10 LM 6000's, due online by May 03 (~450 MW).  turbines will be on site shortly w/ construction due to start in April
PPL has entered an LOI to sell the completed plant to a team of investors led by John Hancock Financial (their Arclight division, or something like that)
seeking 20-25 year toll
Electric interconnection is South Acron bus (Lancaster, PA - eastern PJM)
Gas interconnection is direct to Columbia mainline
They are looking for an indicative number this monday, but admitted that it'll stretch out for at least a few weeks.

I'm in Houston through end of today, so please swing by or call me tomorrow at 978-449-9936 if you wish to discuss.  thanks

John C. Llodra
Executive Director, Northeast Power Marketing
UBS Warburg Energy
Office:  978-449-9936
Cell:  978-314-5614
Fax:  978-449-9937
john.llodra@ubswenergy.com